| Plan - A, CDP | |
|---|---|
| On Booking | 10% |
| Within 30 days From Bank Approval | 85% |
| On Possession | Other Charges + 5% |
| Plan - B, CLP | |
|---|---|
| On Booking | 10% |
| Within 30 days from booking | 10% |
| On Excavation | 10% |
| On Ground Floor Casting | 10% |
| On Fourth Floor Casting | 10% |
| On Eight Floor Casting | 12.5% |
| On Twelevth Floor Casting | 10% |
| On Top Floor Casting | 12.5% |
| On Brick Work and Plaster | 10% |
| On Finishing | 5% |
| On Possession | Other Charges |
| Plan - C, Flexi Payment Plan | |||||||
|---|---|---|---|---|---|---|---|
| On Booking | 10% | ||||||
| Within 45 days from booking | 30% | ||||||
| On Ground Floor Casting | 10% | ||||||
| On Fourth Floor Casting | 10% | ||||||
| On Eight Floor Casting | 10% | ||||||
| On Twelveth Floor Casting | 10% | ||||||
| On Top Floor Casting | 10% | ||||||
| On Start of Finishing Work | 10% | ||||||
| On Possession | Other Charges | ||||||
|
|||||||
| On casting of Top floor slab | 10% of BSP | ||||||
| On start of Finishing work | 10% of BSP | ||||||